- Hospital multi-utility diversion route works to enable the construction of new buildings.
- Stakeholder Management.
- Trial holes/investigations.
- Street works licensing and electronic noticing.
- Design and Diversion of all utilities, HV, LV, National
- Grid Gas, BT and Thames Water, Foul water, 7 European telecom networks and BOC piped oxygen.
- Design and construction of temporary substations.
Design and build for new incoming HV Power Supplies (ICP connection) comprising of approx. 3 km of 11kV trenching and ducting. Load capacity ranging from
1MVA to 6.2MVA.